Two companies at the center of the artificial-intelligence data center investment boom are parting ways, according to a report from the Financial Times. Oracle and alternative investments firm, Blue ...
Larry Ellison’s Oracle is stumbling into the end of the year with its shares taking a beating. The tech firm’s stock has plummeted 30% so far this quarter, CNBC noted Friday. Only four trading days ...
Delayed AI infrastructure projects, rising debt, and weaker-than-expected earnings are reviving dot-com-era fears on Wall Street. Reading time 2 minutes After spending a year making it clear that it ...
Oracle Corporation (NYSE:ORCL) pushed back on December 12 against a report claiming it would finish building data centers for OpenAI in 2028 rather than 2027. The report, published by Bloomberg, said ...
Oracle's quarterly results missed revenue targets, sparking concerns after a report claimed delays in its massive data center projects for OpenAI. However, Oracle insists contractual commitments are ...
Dec 12 : Oracle denied on Friday a media report that it was delaying OpenAI-related data centers, following investor worries over its debt-fueled AI infrastructure buildout. Bloomberg News had earlier ...
[BENGALURU] Oracle denied on Friday (Dec 12) a media report that it was delaying OpenAI-related data centres, following investor worries over its debt-fuelled artificial intelligence (AI) ...
Dec 12 : Oracle has pushed back the completion dates for some of the data centers it is developing for OpenAI to 2028 from 2027, Bloomberg News reported on Friday citing people familiar with the work.
Oracle Corp (NYSE: ORCL) shares slipped on Friday after Bloomberg reported that some of the company's data centers being built for OpenAI will now be completed in 2028 instead of 2027. What Happened: ...
Oracle has reportedly delayed some of its data center projects set for OpenAI workloads by as much as a year. The company made the move to delay projects from 2027 to 2028, Bloomberg reports, mostly ...